Client
Salinas Calombolo
Project
Chemical Products Factory
Location
Benguela – Angola
Delivery Time
18 months
Area
5000m2
Client
Salinas Calombolo
Project
Chemical Products Factory
Location
Benguela – Angola
Delivery Time
18 months
Area
5000m2
Start of foundations ensuring the structural stability necessary for subsequent phases as well as the initial structure of the annex buildings.
View Photos
Prefabrication of pipe racks at the factory to take place in parallel with civil construction work on site. The structures will be transported to Angola with pre-assembly completed, allowing for faster, simpler and more efficient local assembly.
View Photos
Assembly of part of the equipment and respective piping for the cell room. Installation of part of the tanks in the central area of the industrial building, as well as in the storage area, and start of assembly of the respective connecting pipes.
View Photos