Alexandre’s House

Fish Processing and Freezing Plant

Project progress

  1. 1st Quarter

    Start of earthworks and foundation works, including excavation, levelling and compaction of the ground, ensuring the geotechnical conditions suited to the main structure, as well as the construction of footings and foundation beams, ensuring the structural stability required for the subsequent construction phases.

    In parallel, work has begun on the ancillary buildings, with preparation of the technical and support areas.

    Alexandre’s House — 1º trimestre
  2. 2nd Quarter

    Completion of the foundations of the main building and ancillary buildings, and start of work on the jetty and the steel structure, which will house the reception, processing and freezing areas.

    In the ancillary buildings, structural work in reinforced concrete continued, ensuring stability and integration with the remaining industrial infrastructure.

    Alexandre’s House — 2º trimestre
  3. 3rd Quarter

    Completion of the steel structure assembly of the main building, including the beams and columns that will support the cladding and roofing panels of the industrial building.

    Continued work on the structures of the warehouse and the technical area, ensuring coordination with the utility networks and the refrigeration systems.

    The administration building has made significant progress, with the structure nearing completion. This building includes office areas, an industrial kitchen and a canteen, designed to provide adequate support for operations and for the personnel assigned to the Fish Processing and Freezing Facility.

    At the jetty, work has started on the marine foundations and the installation of the first support structures.

    Alexandre’s House — 3º trimestre
  4. 4th Quarter

    In the industrial building, work advanced on the reinforced concrete slabs and the assembly of the mezzanines, and the installation of the industrial refrigeration system and the insulation (thermal envelope) works has begun.

    In the warehouses and technical buildings, work continued on the infrastructure (water, sewers and electricity), plastering and the installation of window frames, including the installation of the Transformer Substation.

    In the administration building, canteen and the housing units, work continued on the infrastructure and on the construction of slabs and finishes, with the start of the steel roof structure on the housing units.

    At the jetty, the main structure and the deck have been completed, with the start of the paving and of the support structures for piping and utility networks.
    In the general infrastructure, the external networks advanced, as did the construction of retaining walls.

    Alexandre’s House — 4º trimestre
  5. 5th Quarter

    In the industrial building, activities related to the complex’s special installations are under way, notably the completion of the assembly of the three IQF freezing tunnels and of the insulation works, as well as the final phase of the installation of the ammonia refrigeration network. The remaining industrial refrigeration systems are at an advanced stage of execution. In parallel, the electrical lighting installation works continue, and the installation of the industrial process equipment is being prepared.

    In the remaining buildings, finishing works are progressing. At the jetty, the concreting of the paving continues, and the seawater and freshwater piping networks have already been installed.

    Alexandre’s House — Entreposto de Processamento e Congelação de Pescado