Salinas Calombolo

Chemical Plant

Project progress

  1. 1st Quarter

    Start of the foundation works, ensuring the structural stability required for the subsequent phases, as well as the initial structure of the ancillary buildings.

    Salinas Calombolo — 1º trimestre
  2. 2nd Quarter

    Prefabrication of the pipe racks at the factory, running in parallel with the civil construction works on site. The structures will be shipped to Angola fully pre-assembled, allowing for faster, simpler and more efficient on-site assembly.

    Salinas Calombolo — 2º trimestre
  3. 3rd Quarter

    Installation of part of the equipment and associated piping in the cellroom. Placement of some of the tanks in the central area of the industrial building, as well as in the storage area, and start of the installation of the respective connecting piping.

    Salinas Calombolo — 3º trimestre
  4. 4th Quarter

    Hydraulic and electrical interconnection of the various items of equipment in the industrial building, ensuring the integration of the process circuits and the utility networks required for the operation of the unit.

    Installation and assembly of the main plant support systems, including water desalination and demineralisation, HVAC, fuel purification and power generation systems, which are essential for the continuous operation of the production lines.

    Salinas Calombolo — 4º trimestre
  5. 5th Quarter

    Work on developing the plant’s infrastructure is progressing well, notably the construction of the boundary walls, roads and wastewater drainage systems, including sewer and blackwater networks.

    In the industrial building, the control and power panels have been received and positioned.

    Significant progress has also been made on finishing works, with the installation of aluminium window frames, doors and stonework, as well as the laying of ceramic floor tiles.

    As regards technical infrastructure, work on the electrical networks is still ongoing.

    Salinas Calombolo — 5º trimestre
  6. 6th Quarter

    Completion of the construction and assembly works, including the finalisation of finishes, electrical networks and the remaining technical installations of the industrial unit. Testing, trials and commissioning of the equipment and systems, preparing for the start of production and the final handover of the works.

    Salinas Calombolo - Terminado