Fish Processing and Freezing Facility

Project Overview

‎ ‎ ‎ ‎ ‎
Client
Alexandre’s House

‎
Project
Fish Processing and Freezing Facility

‎
Local
Benguela – Angola

‎
Execution Period
18 meses

‎
Site Area
7100m2

Project Progress

1st quarter

The earthmoving and foundation work began, including excavations, leveling and compaction of the terrain, ensuring the appropriate geotechnical conditions for the construction of the main structure, as well as the execution of footings and foundation beams, guaranteeing the structural stability necessary for the subsequent construction phases.

In parallel, work began on the annex buildings, with the preparation of the technical and support areas.

View Photos

2nd quarter

Completion of the foundations for the main building and annexes, and commencement of work on the pier and metal structure, intended to house the receiving, processing, and freezing areas.

In the annex buildings, structural work continued in reinforced concrete, ensuring stability and integration with the remaining industrial infrastructure.

View Photos

3rd quarter

Completion of the assembly of the main building’s metal structure, including the beams and pillars that will support the cladding and roofing panels of the industrial building.

Continuation of work on the warehouse and technical area structures, ensuring compatibility with utility networks and refrigeration systems.

The administrative building has seen significant progress, with the structure nearing completion. This building integrates office areas, an industrial kitchen, and a cafeteria, designed to ensure adequate support conditions for operations and personnel allocated to the Fish Processing and Freezing Center.

On the pier, the execution of the maritime foundations and the assembly of the first support structures have begun.

View Photos

4th quarter

In the industrial building, progress was made on the reinforced concrete slabs and the mezzanines, with the installation of industrial refrigeration and insulation work beginning.

In the warehouses and technical buildings, work continued on the infrastructure (water, sewage, and electricity), plastering, and window and door frame installation, including the installation of the transformer substation.

In the administrative building and cafeteria, and in the residential buildings, infrastructure work and the execution of slabs and finishes took place, with the start of the metal roof structure in the residential buildings.

On the pier, the main structure and deck were completed, with the start of the pavement and support structures for pipes and networks.

In the general infrastructure, progress was made on the exterior networks and the construction of retaining walls.

View Photos

Menu

Home

About Novanor

Ongoing Work

Projects – Portfólio

News

Contacts

© Novanor 2023, Desenvolvido por Setup Tech, Todos os direitos reservados

default
default
default
default
default

default
default
default
default
default